Managing the Risk of Circuit Breaker Failures 2024-2028
- State-Wide
- In Progress
- RIT-TSubstation
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ...
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.
We are proposing to replace 26 circuit breakers at 11 substations to maintain safe and reliable electricity supply to customers.
The identified need for this project is to continue to provide safe and reliable electricity transmission services in South Australia at a prudent and efficient cost. Specifically, the identified need for this Regulatory Investment Test for Transmission (RIT-T) is to efficiently manage the risk of failure of circuit breakers across 11 substations that are in poor condition and have reached the end of their technical lives.
We have classified this RIT-T as a ‘market benefits’ driven RIT-T as it is being progressed to manage the risk of asset failure and thereby deliver positive net benefits to customers.
A full cost benefit assessment has been undertaken, comparing the risk cost reduction benefits of circuit breaker replacement with the cost of a base case ‘do nothing’ option, together with options considered but not being progressed.
Closing Date: 13 September 2024
Status: Consultation Closed
Closing Date: 25 November 2024
Status: Consultation Closed